Question no 3690 : Mandatory MRP Pre-requisites

In SAP MM/PP as at ECC6.0 EhP6, which of the following are the mandatory pre-requisite for MRP run for a Material ?

(more than one answers)

A)  Plant Parameter.
B)  MRP Group Parameter.
C)  Material Master Accounting data view.
D)  Valid MRP Type in the Material Master MRP 1 data view.
E)  Source List.
.

Click on the "1 comment" button to check the Suggested answers

1 comment:

  1. Answers: A, B, D

    C) Without Accounting data view is OK for MRP run, eg: "UNBW" Material Type can be subjected to MRP without the Accounting data view.
    D) Source Determination via Source List and Quota Arrangement is optional for MRP run.

    ReplyDelete