In SAP PP as at ECC6.0 EhP6, which of the following is the setting for MRP run when the system first looks for a Routing, if Routing was not found, it will then revert to check either the Lot Size dependent data or Lot Size independent data in the Material Master ?
(only one answer)
A) Basic date scheduling.
B) Detail date scheduling.
C) Routing date scheduling.
D) 3 stage date scheduling.
E) Lead time scheduling.
.
Answer: E
Lead time scheduling.
(only one answer)
A) Basic date scheduling.
B) Detail date scheduling.
C) Routing date scheduling.
D) 3 stage date scheduling.
E) Lead time scheduling.
.
Answer: E
Lead time scheduling.