Question no 3667 : MRP for PP

In SAP PP as at ECC6.0 EhP6, which of the following is the setting for MRP run when the system first looks for a Routing, if Routing was not found, it will then revert to check either the Lot Size dependent data or Lot Size independent data in the Material Master ?

(only one answer)

A)  Basic date scheduling.
B)  Detail date scheduling.
C)  Routing date scheduling.
D)  3 stage date scheduling.
E)  Lead time scheduling.
.

Answer: E

Lead time scheduling.