In SAP PM as at ECC6.0 EhP6, which of the following is not true about a Maintenance Notification ?
(more than one answers)
A) It can be assigned to a PM Order to collect costs.
B) It can be generated via Saving a Maintenance Order.
C) It can be assigned with one or more General Task List.
D) It can be created without a reference Object.
E) It can be closed without converting to a Maintenance Order.
.
Click on "1 comment:" for suggested answer
(more than one answers)
A) It can be assigned to a PM Order to collect costs.
B) It can be generated via Saving a Maintenance Order.
C) It can be assigned with one or more General Task List.
D) It can be created without a reference Object.
E) It can be closed without converting to a Maintenance Order.
.
Click on "1 comment:" for suggested answer
Answers: A, C
ReplyDeleteA) no cost collection yet possible for the Notification in PM as at the version mentioned.
B) via an appropriate MO Order Type, a Notification can be generated from an MO.
C) Only one Task List per Notification.
D) Unless field selection was activated.
E) A Notification can stand alone without linking to an MO.