In SAP MM as at ECC6.0 EhP6, which of the following are the similarities of Contract and Scheduling Agreement ?

(more than one answers)

A)  Goods Receipt with reference to them.
B)  Save the documents without a Plant.
C)  Subcontracting scenario.
D)  Both have Value and Quantity based.
E)  Only Goods Receipt for Scheduling Agreement.
.

Answer: C, E

A, E) GR only for SA
B) Central Contract can be created without a Plant but not SA
C) Subcontracting can be for both
D) Qty and Value based are only for Contracts