Question no 3628 : Maintenance Item data

In SAP PM as at ECC6.0 EhP6, which of the following is not assigned to the Maintenance Item ?

(more than one answers)

A)  Scheduling Period.
B)  Call Horizon.
C)  Measuring Point.
D)  Shift Tolerances.
E)  Scheduling time reference.
.

Answer: A, B, C, D, E

All of the above are at the Maintenance Plan Header.