Question no 3629 : Inspection Lot in PM

In SAP PM as at ECC6.0 EhP6, which of the following are the necessary configuration for generating an Inspection Lot when a Maintenance Order is saved ?

(only one answer)

A)  Order Type.
B)  Planning Plant.
C)  Item Category.
D)  Maintenance Plant.
E)  Maintenance Activity Type.
.

Answer: A

AN Inspection Type is assigned to the Order Type for this to happen.