Question no 3588 : Capacity Calculation controls

In SAP PP as at ECC6.0 EhP6, which of the following will have an impact on Capacity calculation for an operation in a Production Order ?

(more than one answers)

A)  In-house production time (material master MRP 2 view)
B)  Operation Control Key (Routing operation)
C)  Queue time (Work Center)
D)  Standard values (Routing operations)
E)  Goods Receipt processing time (material master MRP 2 view)
.

Answer: B, D

A) In-house production time is used for MRP Basic scheduling where the system never looks for a Routing. This time parameter is only for MRP run, when converting a Planned Order to Production Order or manually creating a Production Order; the system will never use this time parameter.
B) Operation Control Key has a configuration that decides if Capacity will be calculated.
C) Queue time and Wait time from the Work Center default to the Operation in the Routing are inter-operation times. 
D) Standard values defined in the work center and later entered in the Operation in the Routing, together with the Formula will result in the Capacity Load.
E)  GR processing time is not used for "Scheduled Dates" but only for MRP run or for "Basic Dates".