In SAP PM as at ECC6.0 EhP6, which of the following Object Dependency type is assigned to the Operation of the Configurable Task List for Operation Selection ?
(only one answer)
A) Selection Condition.
B) Action.
C) Procedure.
D) Net.
E) Pre-Condition.
.
Answer: A
Selection Condition is for selecting an object.
Action and Procedure are for making selection mandatory and set values.
Net is a more complex rule writing usually used for calculations.
Pre-Condition is like (if then else in programming)
(only one answer)
A) Selection Condition.
B) Action.
C) Procedure.
D) Net.
E) Pre-Condition.
.
Answer: A
Selection Condition is for selecting an object.
Action and Procedure are for making selection mandatory and set values.
Net is a more complex rule writing usually used for calculations.
Pre-Condition is like (if then else in programming)