In SAP PP as at ECC6.0 EhP6, select the time parameters can do not affect the calculation of capacity load for work center of an operation in a production order ?
(more than one answers)
A) Setup time.
B) Processing time.
C) Wait time.
D) Move time.
E) Queue time.
.
Answer: C, D, E
Wait, Move, Queue are all inter-operation times with no impact on capacity loads of the work center.