In SAP PM ECC6.0, the Material Where-Used List Report of IW13 provide the following information ?
(more then one answers)
A) Total Planned Reservations.
B) Total Goods Issue with reference to Reservation.
C) Total Goods Issue without reference to Reservation.
D) Total Cost of Planned Goods Issue.
E) Total Cost of Unplanned Goods Issue.
.
(more then one answers)
A) Total Planned Reservations.
B) Total Goods Issue with reference to Reservation.
C) Total Goods Issue without reference to Reservation.
D) Total Cost of Planned Goods Issue.
E) Total Cost of Unplanned Goods Issue.
.
Answer: A, B, C
ReplyDeleteSo far in ECC6.0, only quantities information in the IW13 report.
ReplyDelete