Question no 1974 : Time-Independent Pricing Condition

In SAP MM Procurement as at ECC6.0, which of the following Purchasing Document allows you to enter Pricing Condition that is Period Independent ?

(only one answer)

A)    Purchase Requisition.
B)    Purchase Order.
C)    Contract.
D)    Scheduling Agreement.
E)    Purchasing Info Record.
.

2 comments:

  1. The Purchasing Requisition only has a estimated Price for each line item. The estimated Price is read from the material master Accounting view. While the Prices at the Contract, SA, and PIR are all time-dependent. The Purchase Order prices conditions are all time-independent.