Question no : 139 PM Preventive Calibration

In SAP QM/PM, For QM application to Test Equipment Calibration, during the Usage Decision; what are the possible intergrations ?

I)     UD can Release or Block the equipment from further usage.
II)    UD allows updating of measurement documents to mesauring points of the Equipment.
III)   Adjust the Cycle modification factor of hte Maintennace Plan.
IV)   Technically close or complete the PM order in the background.

A)    I, II
B)    III, IV
C)    I, II, III
D)    II, III, IV
E)    I, II, III, IV
.