Question 4082 : Alternative dates in Change Number in ECM system

In SAP Engineering Change Management as at S/4 1909, which of the following are the features of "Alternative Dates" in a Change Number ?

(more than one answers)

A) one or more Alternative Dates can be applied to a Change Number.
B) All Alternative Dates must be applied to all the Objects in a Change Number.
C) Alternative Dates feature and Shift Dates feature is the same.
D) Different Objects in a Change Number can be applied to different Alternative Dates.
E) All Objects in the Change Number must be applied to Alternative Dates.
.

Answer: A, D

A) An existing Change Number can be assigned with multiple Alternative Dates.
B, D, E) One can flexibly assign any or selected objects in the Change Number to different Alternative dates entered in the Change Number.
C) Shift Date permanently shifts the original date of the Change Number while Alternative Dates are add-on dates to the original date of the Change Number.