In SAP Production Planing as at S/4 1909, which of the following "Planning Time fields" are valid ?
(more than one answers)
A. Plant Parameter Planning Horizon.
B. MRP Group Parameter Planning Horizon.
C. MRP 1 view Time Fence.
D. PPDS Planning Horizon.
E. SNP Horizon.
.
Answer: C, D
A, B) The Classic Planning Horizon in Plant Parameter (OPPQ) and MRP Group (OPPR) no longer available.
C) Planning Time Fence in MRP 1 view is still valid which effectively seen in MD04 and APO Product view.
D) PPDS Horizon can be set for each Advanced Planning Version.
E) The APO SNP module is not yet available in S/4 1909.
(more than one answers)
A. Plant Parameter Planning Horizon.
B. MRP Group Parameter Planning Horizon.
C. MRP 1 view Time Fence.
D. PPDS Planning Horizon.
E. SNP Horizon.
.
Answer: C, D
A, B) The Classic Planning Horizon in Plant Parameter (OPPQ) and MRP Group (OPPR) no longer available.
C) Planning Time Fence in MRP 1 view is still valid which effectively seen in MD04 and APO Product view.
D) PPDS Horizon can be set for each Advanced Planning Version.
E) The APO SNP module is not yet available in S/4 1909.