In SAP Production Planning & Detail Scheduling, which of the following MRP Types are allowed for "Advanced Planning" in S/4 1909 ?
(More than one answers)
A. PD
B. VB
C. X0
D. M0
E. R1
.
Answer: A, B, D, E
Basically, MRP Type "X0" used to be for when APO was a separate entity (system), now in S/4; PPDS runs recognizes MRP Types with Procedure "MRP, "MPS", and "CBP".
(More than one answers)
A. PD
B. VB
C. X0
D. M0
E. R1
.
Answer: A, B, D, E
Basically, MRP Type "X0" used to be for when APO was a separate entity (system), now in S/4; PPDS runs recognizes MRP Types with Procedure "MRP, "MPS", and "CBP".
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.