In SAP Quality Management, in which of the following setup that the entry of the Sampling Procedure is mandatory when the Inspection Characteristics is assigned to the Operation in the Inspection Plan ?
(only one answer)
A. When the Material Master QM view is not assigned with a Sampling Procedure.
B. When the Inspection Plan Header was not assigned with a Sampling Procedure.
C. When the Inspection Type assigned in the QM view was configured with Sampling Procedure requirement.
D. When the Master Inspection Characteristic is set with Sampling Procedure requirement indicator.
E. When the Inspection Task List Profile is set with Sampling Procedure requirement.
Answer: D