In SAP Production Planning as at ECC6 EhP8, when the Requirements falls within the Planning Horizon, the system set the which of the following flags.
(only one answer)
A. NETCH and NETPL.
B. NETCH only.
C. NETPL only.
D. NEUPL only.
E. NEUTPL and NETPL.
.
Answer: A
NETCH is Net Change.
NETPL is Net Change within Planning Horizon.
NEUPL is Regenerative MRP.
NEUPL is available in Plant level MRP run in MD01 and MDBT.
NETCH is flagged regardless or the Planning Horizon.
NETPL is flagged when Demand falls within the Planning Horizon.