Question no 3981 : MRP run with or without Lead Time Scheduling

In SAP Production Planning and Execution, an MRP will use the In-house Production time or Lot-size dependent Lead times in the Work Scheduling view in which of the following circumstances ?

(more than one answers)

A. When Routing is not found.
B. When BOM and Routing both were not found.
C. When Scheduling mode is "1" Basic dates in MD01 or MD02.
D. When Scheduling mode is "2" and both BOM and Routing were not found.
E. When Scheduling mode is "2" and Routing is not found.
.

Answer: A, C, E

In MD01, MDBT or MD02, the Scheduling selection field allows to shows either "1" or "2":
  • "1" Basic date dictates MRP run will use either In-house Production time or Work Scheduling view's Lot size dependent data for scheduling.
  • "2" Lead time scheduling dictates the system will try to find a Routing for scheduling but if a Routing is not found then it will revert to use either In-house Production time or Work Scheduling view's Lot size dependent data for scheduling.