This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Saturday, November 26, 2022

Question no 3954 : Performing Costing run using CK11N

In SAP Controlling, which of the following are TRUE when creating a Cost Estimate using CK11N ? 

(more than one answers)
A) The Costing data views of Material Master must exist prior to performing CK11N.
B) A Costing Variant is required in the Costing and Accounting data view to default to CK11N.
C) The Costing Lot Size in the Material Master Costing view is necessary for CK11N.
D) Valuation date can be selected before executing Costing roll-up in CK11N.
E) A Costing Lot Size can be entered before executing Costing roll-up in CK11N.
.

Answers: D, E

A, C) The Costing data views for FG or Raw Materials are not necessary for CK11N and in fact the Material Master Costing view will be generated automatically when performing CK11N.
B) No, there are no Costing Variant assignment int he Material Master and in fact it is entered in the initial screen of CK11N.
D) Both Quantity Structure Explosion Date and Valuation Date can be entered in the initial screen of CK11N before executing the Costing run.
E) Besides the Costing Lot Size and Costing Variant, the Costing Version can be entered in the initial screen.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.