This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, November 14, 2022

Question no 3953 : Requirement Type for Planned Independent Requirement

In SAP Production Planning, which of the following Strategy do not have Requirement Type assigned for Planned Independent Requirement ?

(only one answer)

A) Strategy 10.
B) Strategy 20.
C) Strategy 30.
D) Strategy 40.
E) Strategy 50.

Answer: Strategy 20

A, C, D) Strategy 10, 30, 40 are all Make-to-Strategy Strategy where PIR is considered and therefore the Requirement Type for PIR can be found in the Strategy.
E) Strategy 50 is Make-to-Order Strategy "Planning without Final Assembly" where the PIR is allowed and used for planning Materials below the Finished Product. Only when Sales Order of the Finished Goods is entered that the FG's Planned Order can be converted to Production Order.




No comments:

Post a Comment

Note: Only a member of this blog may post a comment.