In SAP ECC 6.0 Ehp7, use the following data to calculate the Cost of the Raw Material.
Finished Goods with Assembly Scrap Factor 20%
Raw Material with Component Scrap Factor 5%
BOM show 1 pc of Raw Material to product 1 pc of Finished Goods
Raw Material MAP is $10/pc
What is the Cost of the Raw Material ?
(only one answer)
A) $12.60
B) $12.00
C) $10.00
D) $13.60
E) $18.00
Answer: A
Explanations:
Assembly Scrap Factor 20%
Component Scrap Factor 5%
1+ (1 x 20%) = 1.20
1.20 + (1.20 x 5%) = 1.26
Raw Material Costs is 1.26 x $10 = $12.60
Finished Goods with Assembly Scrap Factor 20%
Raw Material with Component Scrap Factor 5%
BOM show 1 pc of Raw Material to product 1 pc of Finished Goods
Raw Material MAP is $10/pc
What is the Cost of the Raw Material ?
(only one answer)
A) $12.60
B) $12.00
C) $10.00
D) $13.60
E) $18.00
Answer: A
Explanations:
Assembly Scrap Factor 20%
Component Scrap Factor 5%
1+ (1 x 20%) = 1.20
1.20 + (1.20 x 5%) = 1.26
Raw Material Costs is 1.26 x $10 = $12.60