Question no 3927 : Planning Versions in Advanced Planning

In S/4 1809, which of the following are TRUE about Planning Versions in Advanced Planning ?

(more than one answers)

A) Planning Version 000 is the active version.
B) Planning Version 000 in Advanced Planning is mapped to Planned Independent Requirement version "00".
C) Operative Stock Requirements List will show Planning data similar to Planning Version 000 in the Product view in Advanced Planning.
D) When using other than Planning Version 000, all master data must be duplicated to that Planning Version.
E) Simulated Stock Requirement List in Long Term Planning's Scenario is mapped to each of the simulated Planning Versions other than 000 in Advanced Planning.

Answers: A, C

A, C) The Planning Version 000 is always the active version for Advanced Planning and is mapped to the Operative Stock Requirement List (MD04).
B) There are no relationships of the Version in PIR, the only thing that matters is the "active" indicator in the PIR.
D) All other Planning Version other than 000 can use the Operative Master data of version "000".
E) As at 1809, there are no link of LTP to Advanced Planning.