In SAP MM as at ECC6.0 EhP6, which of the following are TRUE about creating Scheduling Agreements (SA)?
(more than one answers)
A) You can create SA with reference to PR.
B) You can create SA with reference to Quotation.
C) You can create SA with reference to PO.
D) You can create SA with reference to Contract.
E) An MRP run can create a SA.
Answers: A, B, D
C) It is not possible to create PO with reference to SA
You can create PO the following ways:
(more than one answers)
A) You can create SA with reference to PR.
B) You can create SA with reference to Quotation.
C) You can create SA with reference to PO.
D) You can create SA with reference to Contract.
E) An MRP run can create a SA.
Answers: A, B, D
C) It is not possible to create PO with reference to SA
You can create PO the following ways:
Create PO with reference to PR, Quotation, another PO, or Contract
E) MRP Run cannot create SA (Scheduling Agreement)
MRP can generate Planned Order, PR, or Delivery Schedule for Scheduling Agreement