Question no 3856 : Inspection Point

In SAP QM as at ECC6.0 EhP6, the Inspection Point can be assigned to which of the following ?

(more than one answers)

A)  Routing Header.
B)  Recipe Header.
C)  General Task List Header.
D)  Inspection Plan Header.
E)  Rate Routing Header.
.

Answers: A, B, C, D, E

A, B, E) Routing, Recipe, Rate Routing assignment of Inspection Point are for In-Process Quality Inspection.
C) Inspection Point in the General Task List Header is for Calibration Scenario.
D) Inspection Plan is for many scenario, the assignment of Inspection Point allow Container in the Inspection Lot for entering multiple Results Recodings.