Question no 3825 : Unit of Measure in Work Scheduling

In SAP PP as at ECC6.0 EhP6, which of the following Unit of Measure can be found in the Work Scheduling data view in the Material Master ?

(more than one answers)

A)  Base Unit of Measure.
B)  Unit of Issue.
C)  Production Unit.
D)  Packing Unit.
E)  Planning Unit.
.

Answers: A, B, C

A) Base UOM is at Client level, it is displayed in this view but not changeable.
B) Goods Issue Unit of Measure for the Manufactured Material.
C) Production Order Unit of Measure for the Manufactured Material.
In SAP, UOM can be:
. Base UOM in Basic 1 view
. Purchasing UOM in Puchasing view
. Production UOM in Work Scheduling view
. Unit of Issue UOM in Plant/Storage 1 view
. WM Unit in Warehouse view
There are no UOM in MRP views for Planning