In SAP PM as at ECC6.0 EhP6, which of the following are the per-requisites for the use of a Material BOM in Plant Maintenance ?
(more than one answers)
A) BOM usage.
B) BOM item category.
C) Item status in the BOM detail.
D) BOM alternative.
E) Material type for Header BOM must be "IBAU".
.
Answers: A, C
A, C) The BOM usage sets the "PM" indicator as the Item Status in the BOM detail.
E) Material Type "IBAU" is not necessary.
(more than one answers)
A) BOM usage.
B) BOM item category.
C) Item status in the BOM detail.
D) BOM alternative.
E) Material type for Header BOM must be "IBAU".
.
Answers: A, C
A, C) The BOM usage sets the "PM" indicator as the Item Status in the BOM detail.
E) Material Type "IBAU" is not necessary.