In SAP QM as at ECC6.0 EhP6, which of the following allows RR after UD ?
(only one answer)
A) Master Inspection Characteristics with "Long Term Characteristics" indicator.
B) Inspection Lot Document Type.
C) Not Possible.
D) Settings in the Quality Info Record.
E) Settings in the Inspection Type detail in the Material Master.
.
Answer: A
Long Term Characteristics allow RR to be done after UD.
(only one answer)
A) Master Inspection Characteristics with "Long Term Characteristics" indicator.
B) Inspection Lot Document Type.
C) Not Possible.
D) Settings in the Quality Info Record.
E) Settings in the Inspection Type detail in the Material Master.
.
Answer: A
Long Term Characteristics allow RR to be done after UD.