In SAP QM as at ECC6.0 EhP7, which of the following scenario of using Maintenance Plan where the Call Object is an Inspection Lot in Standard SAP ?
(only one answer)
A) Calibration.
B) Refurbishment.
C) Asset Under Construction.
D) Corrective.
E) Stability Study.
.
click "1 comment" to view suggested solution
(only one answer)
A) Calibration.
B) Refurbishment.
C) Asset Under Construction.
D) Corrective.
E) Stability Study.
.
click "1 comment" to view suggested solution
Answer: E
ReplyDeleteStability Study via a special Notification type.