In SAP PP as at ECC6.0 EhP6, which of the following are TRUE about Bill of Material ?
(more than one answers)
A) A BOM can be assigned to one or more Plants.
B) A BOM can be created and saved without a Plant.
C) A Material as a BOM Header can be created with more than one BOM with different Usages.
D) A Material as a BOM Header can be created with more than one BOM with different Alternatives.
E) A BOM is always created with an Internal BOM number in the Header.
.
click "1 comment" to view suggested solution
(more than one answers)
A) A BOM can be assigned to one or more Plants.
B) A BOM can be created and saved without a Plant.
C) A Material as a BOM Header can be created with more than one BOM with different Usages.
D) A Material as a BOM Header can be created with more than one BOM with different Alternatives.
E) A BOM is always created with an Internal BOM number in the Header.
.
click "1 comment" to view suggested solution
Answers: A, B, C, D, E
ReplyDeleteA, B) A Group BOM without a Plant can later be assigned to more than one Plants.
C, D) Usages and Alternatives are possible for BOM.
E) All BOM will have an Internal Number to identify it.
Unlike Routing which must be created for a Plant only, it cannot be assigned to multiple Plants (ECC6),
but a Routing can be assigned to one or more assemblies.
BUT a component list cannot be assigned to more than one assembly, each Material BOM is created with a
unique Header Material with combination of Usage and Alternative.