In SAP QM as at ECC6.0 EhP6, which of the following when all other data is valid except the sampling procedure was not found for a QM activated material at GR for PO ?
(only one answer)
A) Inspection Lot generated at "CRTD" status.
B) Inspection Lot generated at "REL" status with default 100% sampling.
C) Inspection Lot will not be generated.
D) Inspection Lot is generated with default sampling procedure from Plant Parameter in the IMG.
E) Inspection Lot generated with "SPNO" status.
.
click "1 comment" for suggested solution
(only one answer)
A) Inspection Lot generated at "CRTD" status.
B) Inspection Lot generated at "REL" status with default 100% sampling.
C) Inspection Lot will not be generated.
D) Inspection Lot is generated with default sampling procedure from Plant Parameter in the IMG.
E) Inspection Lot generated with "SPNO" status.
.
click "1 comment" for suggested solution
Answers: A
ReplyDeleteIf all other QM data is valid, the Inspection Lot is still generated with "CRTD" status without a Sample, until a Sample is entered or calculated; the Inspection Lot cannot be RELEASED.