In SAP QM as at ECC6.0 EhP6, which of the following when all other data is valid except the sampling procedure was not found for a QM activated material at GR for PO ?

(only one answer)

A)  Inspection Lot generated at "CRTD" status.
B)  Inspection Lot generated at "REL" status with default 100% sampling.
C)  Inspection Lot will not be generated.
D)  Inspection Lot is generated with default sampling procedure from Plant Parameter in the IMG.
E)  Inspection Lot generated with "SPNO" status.
.
click "1 comment" for suggested solution

1 comment:

  1. Answers: A

    If all other QM data is valid, the Inspection Lot is still generated with "CRTD" status without a Sample, until a Sample is entered or calculated; the Inspection Lot cannot be RELEASED.