Question no 3745 : Planning File Entry

In SAP MM/PP as at ECC6.0 EhP6, which of the following will automatically creates the Planning File Entry for a Material Master ?

(only one answer)

A)  Valid MRP Type.
B)  Activate Plant Parameter.
C)  MRP Group.
D)  Valid Material Type.
E)  MRP Area.
.
click "1 comment" to view suggested solution

1 comment:

  1. Answer: A 

    A Valid MRP Type means either for MPS, MRP or CBP. 
    MRP Type such as "X0" (no planning) is not a Valid MRP Type. 
    MRP Type such as "PD" (MRP) is a Valid MRP Type.

    ReplyDelete