In SAP PM/QM as at ECC6.0 EhP6, which of the following is the use of same Classification Characteristics assigned to the Measuring Point and Master Inspection Characteristics ?
(only one answer)
A) Inspection Lot creation pre-requisite.
B) Update Calibration results from QM Results Recording to Measurement Documents.
C) Allow Maintenance Plan creation.
D) Link the Equipment Master to the Inspection Lot.
E) All of the above.
.
click "1 comment" for suggested solutions
(only one answer)
A) Inspection Lot creation pre-requisite.
B) Update Calibration results from QM Results Recording to Measurement Documents.
C) Allow Maintenance Plan creation.
D) Link the Equipment Master to the Inspection Lot.
E) All of the above.
.
click "1 comment" for suggested solutions
Answer: B
ReplyDelete