Question no 3723 : MRP Strategy

In SAP PP as at ECC6.0 EhP6, which of the following the MRP Strategy can be found ?

(more then one answers)

A)  Material Master MRP 3 data view.
B)  Material Master MRP 1's MRP area data view.
C)  MRP Group.
D)  MRP Plant Parameter.
E)  Production Version.
.

Answers: A, C

Priority 1 is Material Master MRP 3 data view, if not found then MRP Group.