In SAP MM as at ECC6.0 EhP6, which of the following MRP Type requires an Forecasting Run to Generate the Independent Requirement and later an MRP run to generate the necessary Supplies ?
(only one answer)
A) VB.
B) VM.
C) R1.
D) R2.
E) VV.
.
click "1 comment" to view suggested solution
(only one answer)
A) VB.
B) VM.
C) R1.
D) R2.
E) VV.
.
click "1 comment" to view suggested solution
Answer: E
ReplyDeleteMRP Type "VV" is for MM-Forecasting, where the Forecasting run will generate the Demands for the MRP run next, to create supplies.