In SAP PP as at ECC6.0 EhP6, which of the following are the results of "Lead Time Scheduling" in MRP run ?
(more than one answer)
A) Creation of Production Order.
B) Create Capacity Load.
C) System searches for the Routing first before settling for time data in the Material Master.
D) Creation of a Planned Order with BOM and Routing data.
E) Perform Source Determination.
.
click "1 comment" for suggested solution
(more than one answer)
A) Creation of Production Order.
B) Create Capacity Load.
C) System searches for the Routing first before settling for time data in the Material Master.
D) Creation of a Planned Order with BOM and Routing data.
E) Perform Source Determination.
.
click "1 comment" for suggested solution
Answers: B, C, D
ReplyDeleteDifference between "Basic Date Scheduling" and "Lead Time Scheduling" is the system searches for the Routing, if found will create a Planned Order with the Routing data for scheduling and Capacity Load creation.