In SAP PP as at ECC6.0 EhP6, the following method of creating Planned Independent Requirement is possible EXCEPT ?
(only one answer)
A) Manually by entering quantities and dates.
B) Copy from Planned Independent Requirements from other PIR versions.
C) Automatically by copying the results of Sales and Operations Planning.
D) Automatically by copying the original plan.
E) Automatically by performing an MRP run.
.
click (1 comment) for suggested answer
(only one answer)
A) Manually by entering quantities and dates.
B) Copy from Planned Independent Requirements from other PIR versions.
C) Automatically by copying the results of Sales and Operations Planning.
D) Automatically by copying the original plan.
E) Automatically by performing an MRP run.
.
click (1 comment) for suggested answer
Answer: E
ReplyDeleteIt is important to note that the "Forecasting Run" does generates Independent Requirements for "Forecast based" MRP Type Materials.
Here is another method of the PIR other than those above: Automatically by copying the planned independent requirements of another material, or by copying another planned independent requirements version of the same material.