Question no 3685 : Maintenance Order Closing

In SAP PM as at ECC6.0 EhP7, which of the following is used to determine which cost element is used to credit the cost from the Maintenance Order to the Settlement Receiver ?

(only one answer)

A)  Valuation Variant.
B)  Costing Variant.
C)  Allocation Structure.
D)  Costing Sheet.
E)  Settlement Rule.
.

Answer: C

The Allocation Structure assigned tot he Settlement Profile is used to achieve this.