In SAP MM as at ECC6.0 EhP6, which of the following Purchasing Documents only updates the Purchasing Info Record as the Last Purchasing Document ?
(only one answer)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
Answer: C
PO only create or Update the PIR as the last PO number.
(only one answer)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
Answer: C
PO only create or Update the PIR as the last PO number.