Question no 3660 : Goods Receipt Time

In SAP MM as at ECC6.0 EhP6, which of the following is TRUE when Goods Receipt Processing Time is Zero in the Material Master MRP2 data view ?

(only one answer)

A)  Goods Receipt Date = Stock Available Date.
B)  Opening Date = Order Start Date.
C)  Order Start Date = Goods Receipt Date.
D)  Exception Message created at MRP run.
E)  System will use the Plant Parameter Goods Receipt Time.
.

Answer: A