Question no 3662 : Estimated Cost

In SAP PM as at ECC6.0 EhP6, Cost Estimate in the Maintenance Order is entered via ?

(only one answer)

A)  Value Category.
B)  Cost Element.
C)  Cost Element Group.
D)  Costing Variant.
E)  Valuation Variant.
.

Answer: A