In SAP PP as at ECC6.0 EhP7, which of the following data structure are TRUE about PP Master Data ?

(more than one answers)

A)  A BOM can be assigned to one or more Plants.
B)  A Routing can be assigned to one or more Plants.
C)  A Routing can be assigned to one or more Materials for the same Plant.
D)  A BOM can be created without a Material and later assigned to one or more Materials.
E)   A BOM can be created without a Plant and later assigned to one or more Plants.
.

Answer: A, C, E

A, E) When a BOM is created without a Plant, it saved as a Group BOM, but to use it, you must then later assigned it to one or more Plants.
B) A Routing is created specifically for a Plant.
C) A Routing can be created without a Plant but later assigned to one or more materials.
D) In CS01, minimum data is Material, Usage, and Date.