Question no 3602 : Manufacturing Strategy

In SAP PP as at ECC6.0 EhP6, consider the following statement by the planner "The Final Assembly of some of the Products can only begin when the Customer Order arrives but the Lead Time for these Customer Orders are too short and Forecast is necessary for the rest of the Components with longer procurement lead times".

Which of the following Strategy would you recommend ?

(only one answer)

A)  Strategy 10.
B)  Strategy 20.
C)  Strategy 30.
D)  Strategy 40.
E)  Strategy 50.
.

Answer: E

Strategy 50 Planning without Final Assembly