Question no 3596 : Source List in Source Determination in MRP Run

In SAP PP and MM as at ECC6.0 EhP6, MRP run uses the Source List to determine which of the following in an MRP run ?

(more than one answers)

A)   Production version.
B)   Vendor.
C)   Contract.
D)   Quantity split.
E)   All of the above.

Answer: B, C

ME01
However, Quota Arrangement will allow assignment of Production Version and Ratio for sources for splitting quantities at MRP run.