Question no 3591 : Organizational Units relevant for MRP Planning Runs

In SAP PP as at ECC6.0 EhP6, which of the following Organizational Units are valid and considered for MRP Planning for Planned Order creations ?

(more than one answers)

A)   MRP Area.
B)   Purchasing Organization.
C)   Plant.
D)   Company Code.
E)   Purchasing Group.
.

Answer: A, C

A,C) MRP Area is assigned with Storage Location for MRP at MRP Area activated at MRP1 data view which will have to be considered for Planning Run at the MRP Area level. MRP activation is at the Plant level so as the MRP data views.

B,E) This is not required considering "Planned Order creations" in the statement although Purchasing Group will be required if MRP run was setup to generate Purchase Requisitions. (The Purchasing Group can be defaulted from MRP Plant Parameter T-Code OPPQ)

D) Company Code is only necessary when creating Purchase Orders and not relevant for Planning Runs.