Question no 3590 : P1, P2, P3, P4 MRP Types

In SAP PP as at ECC6.0 EhP6, in conducting the PP workshop, the user notice MRP Type delivered by SAP includes P1, P2, P3, P4, other than the standard PD, how would you response to the use of these variations of MRP Type to the curious user ?

(only one answer)

A)  Treatment of New Demands within the time fence and how the New Procurement Proposal should be death with.
B)  Different time fence periods.
C)  How the different types of Stock Types are treated.
D)  For MRP Type with User Exits.
E)  Tell the user the P1, P2, P3, P4 are not important.
.

Answer: A

Basically 2 treatments for treatment of demands within the time fence:
. ignore and not create a suplly planned order to fulfill the new demand.
. create proposal outside the time fence.