In SAP PM as at ECC6.0 EhP6, the above Stock Requirements is for material T-T120, which of the following correctly describes the scenario above ?
(more than one answers)
A) Material is entered as item category "N" in the Maintenance Order.
B) The Purchase Requisition item is created with item Category "N".
C) The Purchase Requisition item is created with account assignment "F".
D) MRP run was executed to generate the Purchase Requisition for the Order Reservation.
E) Direct Procurement was set in the Special Procurement key for the material T-T120.
.
Answer: A, C
D) normally PR is set to be created at Created or Release Status, therefore both Reservation and PR are created without the need for MRP run.
E) direct procurement is for PP module.
The codes and use of Item Categories in each module can be very different, do not get confused.