In SAP PM as at ECC6.0 EhP6, Unplanned Goods Issue can be executed to a Maintenance Order at which stage of the Maintenance Order ?
(more than one answers)
A) Created Status.
B) Released Status.
C) Locked Status.
D) Technical Completion Status.
E) Business Closing Status.
.
Answer: B, D
Surprising, or not surprising. You can GI to an MO after the MO is TECOed. (via GI others in MIGO then manually enter the material and in the Account Assignment TAB type in the MO manually and SAVE the GI transaction).
After TECO, cost postings into the MO via MIGO, Confirmation, non-stock PO invoice, Service PO invoice can all be executed !
(more than one answers)
A) Created Status.
B) Released Status.
C) Locked Status.
D) Technical Completion Status.
E) Business Closing Status.
.
Answer: B, D
Surprising, or not surprising. You can GI to an MO after the MO is TECOed. (via GI others in MIGO then manually enter the material and in the Account Assignment TAB type in the MO manually and SAVE the GI transaction).
After TECO, cost postings into the MO via MIGO, Confirmation, non-stock PO invoice, Service PO invoice can all be executed !