In SAP MM or PP in MRP planning as at ECC6.0 EhP6, the implementation of "Last Lot Exact" for Quantity determination can be done via which of the following ?

(only one answer)

A)   MRP Type.
B)   Time Fence.
C)   MRP Strategy.
D)   Availability Check Group.
E)   Lot Size Key.
.

1 comment:

  1. Answer: E

    Via the Lot Size Key in the IMG, there is a a parameter setting for "Last Lot Exact".