In SAP MM as at ECC6.0 EhP6, there is a quantity contract with item category 'M' for material group ZT02 for 100,000 pc of $1.00/pc, an exclusion rule was set for material M1 and M2, in the system there are 5 materials M1, M2, M3, M4, M5 with material group ZT02, deduce the scenario with the right source list result from saving the contract above.
(only one answers)
A) only Source list for M3, M4, M5 was created.
B) only Source list for M3, M4, M5 was created with the 'Blocked' indicator.
C) Source list M1, M2 was created with the 'Blocked' indicator and Source list M3, M4, M5 was created.
D) only Source list M1, M2 was created with the 'Blocked' indicator.
E) Source list M3, M4, M5 was created with the 'Blocked' indicator and Source list M1, M2 was created.
.
(only one answers)
A) only Source list for M3, M4, M5 was created.
B) only Source list for M3, M4, M5 was created with the 'Blocked' indicator.
C) Source list M1, M2 was created with the 'Blocked' indicator and Source list M3, M4, M5 was created.
D) only Source list M1, M2 was created with the 'Blocked' indicator.
E) Source list M3, M4, M5 was created with the 'Blocked' indicator and Source list M1, M2 was created.
.
Answer: D
ReplyDeletewith Exclusion indicator set:
ReplyDeleteonly Source list for M1, M2 will be created with the 'Blocked' indicator.
with Exclusion indicator not set:
only Source list for M3, M4, M5 will be created.