In SAP for MM as at ECC6.0 EhP6, UNBW material type delivered by SAP contains the following configuration ?

(more than one answers)

A)   Accounting data view is not available.
B)   Basic and Accounting data view is not available.
C)   Quantity update is set but Value update is not set for selected Plants.
D)   Both Quantity update and Value update are not set for all Plants.
E)   MRP is not possible for materials created with this material type.
.

4 comments:

  1. A, B) UNBW delivered by SAP contains the following data view selection as standard:
    Classification
    MRP
    Purchasing
    PRT
    Basic
    Storage
    Forecasting
    QM
    WM
    Plant Stocks

    (not Accounting)

    ReplyDelete
  2. C, D) UNBW is meant for material to be managed with Qty update but not Value update.

    ReplyDelete
  3. E) MRP planning is allowed since the material is managed by Qty.